Legal Advertisements - Week of September 10, 2026
MIDDLEBOROUGH
HOUSING AUTHORITY
The Middleborough Housing Authority, the Awarding Authority, invites sealed bids from Contractors for the Storage Building and Parking at the Riverview Development for the Middleborough Housing Authority in Middleborough Massachusetts, in accordance with the documents prepared by TBA Architects, Inc..
The Project consists of: All work indicated in the contract drawings and specifications with the intent of constructing a new wood framed storage building, parking lot improvements, and memorial plaza. A new single story wood framed, shingle and metal panel sided building on frost wall foundation with asphalt shingle roofing. New mechanical and electrical systems. Modifications to an existing parking lot for increased parking and access to the new building. Relocation of a memorial plaza with new paving and reuse of existing paving for stone walls. Compliance with Conservation Order of Conditions.
The work is estimated to cost $ 327,460.00
Bids are subject to M.G.L. c.149 §44A-J & to minimum wage rates as required by M.G.L. c.149 §§26 to 27H inclusive.
General bidders must be certified by the Division of Capital Asset Management and Maintenance (DCAMM) in the category of work: General Construction and must submit a current DCAM Certificate of Eligibility and a signed Update Statement (CQ3).
General Bids will be received until 2:00 PM on Wednesday, October 14, 2026 and publicly opened, forthwith.
Filed sub-bids for the trades listed below will be received until 2:00 PM on Wednesday, September 30, 2026
and opened forthwith.
Filed sub-bidders must be DCAMM certified for the trades listed below and bidders must include a current DCAMM Sub-Bidder Certificate of Eligibility and a signed DCAMM Sub-Bidder’s Update Statement.
SUBTRADES: Section 23.00.00 HVAC, Section 26.00.00 Electrical
This project is being electronically bid. All bids must be prepared and submitted online through Projectdoc.com. Hard copy bids will not be accepted by the Awarding Authority. For assistance, contact Projectdog, Inc. at (978) 499-9014.
Bid Forms and Contract Documents will be available electronically at no cost on Projectdoc.com under Project ID #261972, beginning September 9, 2026.
General bids and sub-bids shall be accompanied by a bid deposit that is not less than five (5%) of the greatest possible bid amount and made payable to the Middleborough Housing Authority.
PRE-BID CONFERENCE / SITE VISIT:
Date and Time: between 1:00 P.M. and 2:00 P.M. on Thursday, September 17, 2026. Address: 8 Benton St., Middleborough, MA 02346
Instructions: Meet in the circle at the bottom of the drive.
TOWN OF MIDDLEBOROUGH
CONSERVATION COMMISSION
The Middleborough Conservation Commission will hold a hearing under M.G.L. c. 131, s.40, the Wetlands Protection Act, for an Amended Order of Conditions to extend the proposed dwelling 12’ further to the north and to move a portion of the garage and driveway 15’ away from the eastern bordering vegetated wetland at 7 Winter Street, Map 16, Lot 5147. Hearing has been requested by Dennis Welch. Hearing will be held September 17, 2026 at 7:00 PM in the Select Board Meeting Room, at the Town Hall, 10 Nickerson Avenue and via remote.
Join Zoom meeting: https://us06web.zoom.us/j/89217424217
Nancy Ockers, Chair
Diane Stewart, 1st Co-Vice Chair
Keri Gallagher, 2nd Co-Vice Chair
Gerard Boissonneault
Bart Devine
Adam Guaraldi
TOWN OF MIDDLEBOROUGH
CONSERVATION COMMISSION
The Middleborough Conservation Commission will hold a hearing under M.G.L. c. 131, s.40, the Wetlands Protection Act, to propose the construction of a warehouse with a total area of 928,000 square feet. Access will be provided via widening Wareham Street within the 200’ Riverfront buffer zone. Also proposed are trailer spaces, parking spaces, and loading docks. A portion of the proposed plan requires filling in a small area of the bordering vegetated wetlands which would then be replicated slightly north adjoining the same bordering vegetated wetland at 678 Wareham Street & Lots off Wareham Street, Map 109, Lots 2963, 3935,4084 & 4675 and Map 110, Lots 4183, 4928, 5116, 4299. Hearing has been requested by Peter Gerrity, South Shore Logistics Park, LLC. Hearing will be held September 17, 2026 at 7:15 PM in the Conference Room, at the Middleborough Police Station, 350 Wood Street and via remote.
Join Zoom meeting: https://us06web.zoom.us/j/89217424217
Nancy Ockers, Chair
Diane Stewart, 1st Co-Vice Chair
Keri Gallagher, 2nd Co-Vice Chair
Gerard Boissonneault
Bart Devine
Adam Guaraldi
TOWN OF MIDDLEBOROUGH
PLANNING BOARD
LEGAL ADVERTISEMENT
In accordance with M.G.L. Chapter 40A, Section 5 as amended, the Planning Board will hold three separate public hearings on Tuesday, October 6, 2026, beginning at 6:30 PM within the Select Board’s Meeting Room, Town Hall, 10 Nickerson Avenue, Middleborough, MA, for the purpose of providing interested parties with an opportunity to comment on the proposed amendments to the Town of Middleborough Chapter 275 Zoning By-laws as follows:
Amendment to Section 2.4 – Zoning Map - Rezone a portion of Assessor’s Map 65, Lot 5659 and Assessor’s Map 66, Lots 3342, 3348, and 5727 from Residential A (RA) to General Use (GU).
Battery Energy Storage Systems (BESS) - Section 2.2 Overlay Districts – Battery Energy Storage System District (BESSD), Section 2.4 – Zoning Map; Section 3.0 Table of Uses – D. Commercial Uses; and ADD Section 8.7 - Battery Energy Storage System (BESS) Bylaw
Prohibition of Data Centers –Section 3.0 Table of Uses – D. Commercial Uses; and Section 10.2 General Bylaw Definitions
The complete text for the proposed amendments is available for inspection within the Planning Department, Town Hall Annex, 20 Center Street, 2nd Floor, Middleborough, MA, Mon. 8AM – 6PM, Tues. - Thurs. 8 AM – 5 PM and Fri. 8 - 12 PM or via emailing BradleyL@middleboroughma.gov. Any person interested in or wishing to be heard on the proposed amendments should appear at the time and place designated.
MIDDLEBOROUGH PLANNING BOARD
Allin J. Frawley, Chairman
Nancy Kefalis, Vice Chair
Tracie Craig-McGee
William B. Garceau
Anders Martenson, IV
David Dias – Associate Member
September 10, 2026 and September 17, 2026
Nemasket Week
TOWN OF MIDDLEBOROUGH
SELECT BOARD
The Middleborough Select Board will hold a public hearing in the Select Board Meeting Room Town Hall, 10 Nickerson Avenue, Middleborough, MA on Monday, September 21, 2026 at 7:30 PM, for the purpose of discussing an application filed by Jason Youngquist, Outback Engineering for a Special Permit under the Water Resource Protection District By-Law to allow the restoration of 1,740 s.f. of disturbed land within the 25’ no touch wetland buffer in a WRPD Zone 3. The property is located at 485 R Wareham Street in the General Use X (GUX) and CBD Overlay Zoning District and the Water Resource Protection District (WRPD) Zone 3. This is shown on Assessors Map 88, Lot 5733. Anyone wishing to be heard on this matter should appear at the time and place designated.
Teresa Farley, Chair
Thomas White, Vice Chair
Brian Giovanoni
William Pike, Jr.
Tracie Craig-McGee
TOWN OF MIDDLEBOROUGH SELECT BOARD
Publish: September 3, 2026 and September 10, 2026
Nemasket Week
TOWN OF MIDDLEBOROUGH
SELECT BOARD
The Middleborough Select Board will hold a public hearing in the Select Board Meeting Room Town Hall, 10 Nickerson Avenue, Middleborough, MA on Monday, September 28, 2026 at 7:30 PM, for the purpose of discussing an application filed by Aaron Guazzaloca, Weston & Sampson for a Special Permit under the Water Resource Protection District By-Law to allow for the construction of a new 13,930 s.f. water treatment facility for the Middleborough Water Department at the site of the Miller Street Well at 42 Miller Street, Map 80 Lot 5151, as well as site improvements at the Rock Village Wells site, 58 Miller Street, Map 87 Lot 293, and the Tispaquin Wells site, 389 Wareham Street, Map 80, Lot 1093. All sites are located in the WRPD Z1 and Z2. All sites are currently used to treat potable water and the use will not change. There will be a maximum of six employees on the largest shift. The properties are located at 42 Miller Street (Map 80, Lot 5151), 58 Miller Street (Map 87, Lot 293), and 389 Wareham Street (Map 80, Lot 1093) in the General Use and Residence Rural Zoning Districts and the Water Resource Protection District (WRPD) Zone 1 and Zone 2 (all). Anyone wishing to be heard on this matter should appear at the time and place designated.
Teresa Farley, Chair
Thomas White, Vice Chair
Brian Giovanoni
William Pike, Jr.
Tracie Craig-McGee
TOWN OF MIDDLEBOROUGH SELECT BOARD
Publish: September 10, 2026 and September 17, 2026
Nemasket Week
MIDDLEBOROUGH
HOUSING AUTHORITY
The Middleborough Housing Authority, the Awarding Authority, invites sealed bids from Contractors for the 667-1 Nemasket Apartments Door & Hardware Replacement REBID for the Middleborough Housing Authority in Middleborough Massachusetts, in accordance with the documents prepared by TBA Architects, Inc.
The Project consists of: REBID Nemasket Apartments 667-1 replacement of residential building wood doors in existing frames, replacement of door hardware at all exterior and vestibule doors, and replacement of doors and frames at the Community Building.
The work is estimated to cost $ 79,599
Bids are subject to M.G.L. c.149 §44A-J & to minimum wage rates as required by M.G.L. c.l49 §§26 to 27H inclusive.
General Bids will be received until 2:00 p.m., Wednesday, September 23, 2026 and publicly opened, forthwith.
This project is being Electronically Bid (E-Bid). All bids shall be prepared and submitted online at Projectdoc.com and received no later than the date & time specified above. Hard copy bids will not be accepted by the Awarding Authority. For assistance, contact Projectdog, Inc. at 978.499.9014.
General bids shall be accompanied by a bid deposit that is not less than five (5%) of the greatest possible bid amount (considering all alternates) and made payable to the Middleborough Housing Authority.
Bid Forms and Contract Documents will be available in electronic form and without cost or charge at Projectdoc.com, project ID 261971, beginning Wednesday, September 9, 2026. Persons desiring hard copies of the documents shall be solely responsible for all printing costs.
The Contractor and all subcontractors (collectively referred to as “the Contractor”) agree to strive to achieve minority and women workforce participation. The Workforce Participation benchmark is set at 6.9% for women and 15.3% for minorities. The Workforce benchmark percentages are a statutory requirement under MGL c. 149 §44A(2)(G).
The job site and/or existing building will be available for inspection between 2:00 P.M. and 3:00 P.M. on Thursday, September 17, 2026.